Title: Actions Related to the 8815 - Mineta San José International Airport - Terminal B South Ramp Reconstruction - Phases 2 & 3 Project.
Sponsors: City Council
Attachments: 1. Memorandum, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

...Title

Actions Related to the 8815 - Mineta San José International Airport - Terminal B South Ramp Reconstruction - Phases 2 & 3 Project.

...Recommendations

Adopt a resolution authorizing the Director of Public Works to:

a.                     Award and execute the 8815 - Mineta San José International Airport - Terminal B South Ramp Reconstruction - Phases 2 & 3 project to the low bidder, Granite Rock Company for the base bid and Add Alternate No. 1 in an amount of $10,863,767.20, contingent upon the award and execution of an Airport Improvement Program grant from the Federal Aviation Administration in a minimum amount of $10,262,000;

b.                     Establish a construction contingency of ten percent of the amount of the construction contract for the Project; and

c.                     Issue any change orders up to the amount of the contingency.

CEQA: Determination of Consistency with the Norman Y. Mineta San José International Airport Master Plan Update Project Final Environmental Impact Report as supplemented, and Addenda thereto (Resolution Nos. 67380 and 71451), File No. PP16-113. (Public Works/Airport)