...Title
Report on Bids and Award of Construction Contract for 10186 - Yard Piping Improvements Phase 3 Project at the San José-Santa Clara Regional Wastewater Facility.
...Recommendations
(a) Accept the report on bids and award of construction contract to the lowest responsive, responsible bidder, Michels Trenchless, Inc., in the amount of $19,490,000, for the 10186 - Yard Piping Improvements Phase 3 Project; and
(b) Approve a 10% construction contingency in the amount of $1,949,000.
CEQA: Addendum to the Environmental Impact Report for the San José/Santa Clara Water Pollution Control Plant Master Plan (SCH# 2011052074), Yard Piping and Road Improvements Project, File No. PP19-063. (Environmental Services/Public Works)