...Title
Report on Bids and Award of Construction Contract for 9850 - Yard Piping Improvements Phase 2 Project at the San José-Santa Clara Regional Wastewater Facility.
...Recommendations
(a) Accept the report on bids and award of construction contract to the lowest responsive, responsible bidder, Michels Trenchless, Inc., in the amount of $16,855,430, for the 9850 - Yard Piping Improvements Phase 2 Project and approve a 15% construction contingency in the amount of $2,528,315.
(b) Adopt the following 2022-2023 Appropriation Ordinance Amendments in the San José-Santa Clara Treatment Plant Capital Fund:
(1) Decrease the Digester and Thickener Facilities Upgrade appropriation to the Environmental Services Department by $2,300,000; and
(2) Increase the Yard Piping and Road Improvements appropriation to the Environmental Services Department by $2,300,000.
CEQA: Addendum to the Environmental Impact Report for the San José/Santa Clara Water Pollution Control Plant Master Plan, Yard Piping and Road Improvements Project, File No. PP19-063. (Environmental Services/Public Works/City Manager)