Construction Contingency Increase for the 7382-Digester and Thickener Facilities Upgrade Project at the San José-Santa Clara Regional Wastewater Facility.
...Recommendations
Approve a $3,107,049 increase to the construction contingency amount of $67,490,625 for a revised total contingency amount of $70,597,674, to provide funding for the City’s negotiated settlement of a loss of productivity claim and changes to the Project control system increasing the not-to-exceed amount from $175,415,625 to a total revised contract amount not-to-exceed $178,522,674 for the 7382 - Digester and Thickener Facilities Upgrade Project.
CEQA: The San José-Santa Clara Regional Wastewater Facility Digester and Thickener Facilities Upgrade Project Mitigated Negative Declaration, File No. PP15-055. (Environmental Services/Public Works)