San Jose Ca.Gov
File #: 22-904    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 5/31/2022 In control: City Council
On agenda: 6/14/2022 Final action:
Title: Approval of a Construction Contingency Increase for the Tech Interactive Blue Tile Replacement Project at the Tech Museum of Innovation.
Attachments: 1. Memorandum

...Title

Approval of a Construction Contingency Increase for the Tech Interactive Blue Tile Replacement Project at the Tech Museum of Innovation.

...Recommendations

Approve an increase in the construction contingency for the Tech Interactive Blue Tile Replacement Project at the Tech Museum of Innovation in an amount of $120,000, from $115,500 to $235,500, to pay for additional work completed by the Contractor due to unforeseen project elements.

CEQA: Categorically Exempt, File No. ER22-147, CEQA Guidelines Section 15301 Existing Facilities. Council District 3. (Public Works)