...Title
Construction Contingency Increase for the 7418 - Cogeneration Facility Project at the San José - Santa Clara Regional Wastewater Facility and Appropriation Amendments.
...Recommendations
(a) Approve a $1,900,000 increase to the owner-controlled construction contingency for the 7418 - Cogeneration Facility Project (“Project”) for a revised contingency in an amount not to exceed $10,188,000.
(b) Adopt a resolution authorizing the City Manager to negotiate and execute amendments to the Design-Build Contract to include additional work and services required to complete the Project or requested by the City, pay for costs resulting from the COVID-19 pandemic and increase the Guaranteed Maximum Price from $91,172,000 to $93,072,000.
(c) Adopt the following 2020-2021 Appropriation Ordinance Amendments in the San José-Santa Clara Treatment Plant Capital Fund:
(1) Decrease the Nitrification Clarifier Rehabilitation appropriation to the Environmental Services Department by $1,900,000; and
(2) Increase the Energy Generation Improvements appropriation to the Environmental Services Department by $1,900,000.
CEQA: San José/Santa Clara Regional Wastewater Facility Cogenerator Project Mitigated Negative Declaration, File No. PP14-005 and Addendum Mitigated Negative Declaration, File No. PP16-009. (Environmental Services/Public Works/City Manager)