...Title
Report on Bids and Award of Construction Contract for 7759 - Switchgear M4 Replacement and G3 and G3a Removal Project at the San José -Santa Clara Regional Wastewater Facility.
...Recommendations
Report on bids and award of construction contract for 7759 - Switchgear M4 Replacement and G3 & G3A Removal Project to the lowest responsive bidder, Blocka Construction, Inc., in the amount of $5,519,000, and approve a 15 percent construction contingency in the amount of $827,850.
CEQA: Categorically Exempt File No. PP18-107, CEQA Guidelines Section 15301 (b), Existing Facilities. (Environmental Services/Public Works)