Actions Related to the 9375 - Market Street Garage Improvements Project.
...Recommendations
(a) Approve an increase to the construction contingency for 9375 - Market Street Garage Improvements Project from 15% to 34%, in the amount of $1,156,215 resulting in a new total contingency amount of $2,069,016.
(b) Adopt the following Fiscal Year 2025-2026 Appropriation Ordinance amendments in the General-Purpose Parking Capital Fund:
(1) Increase the Garage Façade Improvements appropriation to the Department of Transportation by $1,831,000; and
(2) Decrease the Unrestricted Ending Fund Balance by $1,831,000.
CEQA: Categorically Exempt, File No. ER20-225, CEQA Guidelines Section 15301, Existing Facilities. Council District 3. (Public Works/Transportation/City Manager)