Title: Actions Related to the 7232 - Trail: Three Creeks Pedestrian Bridge Over Los Gatos Creek Project.
Attachments: 1. Memorandum

...Title

Actions Related to the 7232 - Trail: Three Creeks Pedestrian Bridge Over Los Gatos Creek Project.

...Recommendations

(a) Adopt a resolution authorizing the Director of Public Works to negotiate and execute one or more change orders to the 7232 - Trail: Three Creeks Pedestrian Bridge Over Los Gatos Creek construction contract with Gordon N. Ball, Inc. to do the following:

 (1) Increase the current base contract amount by up to $700,000, from $1,786,247 to a revised contract amount not to exceed $2,486,246, subject to the condition that this increase is a full settlement of all cost increases; and

 (2) Extend the completion date of the work by more than 180 calendar days.

(b) Authorize increasing the contract contingency by $55,806, from $162,745 to $218,551, to provide for any unexpected work needed for the proper completion of the project.

CEQA: Environmental Impact Report for the Three Creeks Trail Pedestrian Bridge Project, File No. PP13-085. Council District 6. (Public Works)