Title: Construction Contingency Increase for the 10186 - Yard Piping Improvements Phase 3 Project at the San José-Santa Clara Regional Wastewater Facility.
Attachments: 1. Memorandum

...Title

Construction Contingency Increase for the 10186 - Yard Piping Improvements Phase 3 Project at the San José-Santa Clara Regional Wastewater Facility.

...Recommendations

Approve an increase to the construction contingency from 10% to 18%, in the amount of $1,540,000, from $1,949,000 to $3,489,000 for the 10186 - Yard Piping Improvements Phase 3 Project.

CEQA: Addendum to the Environmental Impact Report for the San José/Santa Clara Water Pollution Control Plant Master Plan (Resolution No. 76858), Yard Piping and Road Improvements Project, File No. PP19-063. (Environmental Services)