File #: 18-285    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 2/22/2018 In control: Public Works Department
On agenda: 3/20/2018 Final action:
Title: Report on Bids and Award of Contract for the 8666-Sanitary Sewer Repairs 2017-18 Package II Project.
Sponsors: City Council
Attachments: 1. Memorandum
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

...Title

Report on Bids and Award of Contract for the 8666-Sanitary Sewer Repairs 2017-18 Package II Project.

...Recommendations

Report on bids and award of contract for the 8666-Sanitary Sewer Repairs 2017-18 Package II to the low bidder, JMB Construction Inc., in the amount of $1,310,540, and approve a contingency in the amount of $131,054.

CEQA: Exempt, File No. PP17-029. Council Districts 3, 5 & 8. (Public Works)