Report on Bids and Award of Contract for the 10283 - Sanitary Sewer Repairs Fiscal Year 2023-2024 Package IV Project.
...Recommendations
(a) Report on bids and award of contract for the construction of 10283 - Sanitary Sewer Repairs Fiscal Year 2023-2024 Package IV Project, to the lowest responsive, responsible bidder, Devaney Engineering, Inc., in the amount of $1,843,285; and
(b) Approve a 10% contingency in the amount of $184,328.
CEQA: Categorically Exempt, File No. ER23-189. CEQA Guidelines Sections 15301(b) Existing Facilities and 15302(c) Replacement or Reconstruction. (Public Works)