San Jose Ca.Gov
File #: 22-217    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 2/14/2022 In control: City Council
On agenda: 3/1/2022 Final action:
Title: Actions Related to the Construction Contract for the ESUHSD Oak Grove Community Wi-Fi Infrastructure and Digital Inclusion Program.
Attachments: 1. Memorandum, 2. Resolution

...Title

Actions Related to the Construction Contract for the ESUHSD Oak Grove Community Wi-Fi Infrastructure and Digital Inclusion Program.

...Recommendations

Adopt a resolution authorizing the Director of Public Works to:

(a) Award and execute a contract for the construction of the ESUHSD Oak Grove Community Wi-Fi Infrastructure Project, to the lowest responsive, responsible bidder in an amount not to exceed $2,000,000; and

(b) Decide any timely bid protest(s) and make the City’s final determination as to the lowest responsive bidder that is responsible as needed to award the contract; and

(c) Establish a construction contingency of up to 10% percent of the amount of the construction contract for the Project.

CEQA:  Statutorily Exempt, File No. PP17-001, CEQA Guidelines Section 15262, Feasibility and Planning Studies with no commitment to future actions. Council District 2. (Public Works/Library)