...Title
Construction Contingency Increase for the 7731 - Nitrification Clarifier Rehabilitation - Phase 1 Project at the San José-Santa Clara Regional Wastewater Facility.
...Recommendations
Approve a $5,200,000 increase to the original construction contingency amount of $5,237,000 for a revised total contingency amount of $10,437,000, increasing the not-to-exceed amount of the contract from $31,421,000 to a total revised contract amount not-to-exceed of $36,621,000, and a 218 workday time extension to the project substantial completion date for the 7731 - Nitrification Clarifier Rehabilitation - Phase 1 Project.
CEQA: Categorically Exempt, File No. PP17-049, CEQA Guidelines Section 15301, Existing Facilities. (Environmental Services/Public Works)