San Jose Ca.Gov
File #: 23-1030    Version: 1
Type: Strategic Support Status: Agenda Ready
File created: 8/1/2023 In control: City Council
On agenda: 8/15/2023 Final action:
Title: Actions Related to the 9157 - Fire Station No. 8 - Relocation (2018 Measure T) Project.
Attachments: 1. Memorandum, 2. Resolution

...Title

Actions Related to the 9157 - Fire Station No. 8 - Relocation (2018 Measure T) Project.

...Recommendations

(a) Adopt a resolution adopting the Fire Station No. 8 Relocation Project Initial Study/Negative Mitigated Negative Declaration (File No. ER 22-063) and the associated Mitigation Monitoring and Reporting Program, in accordance with the California Environmental Quality Act (CEQA).

(b) Report on bids and award of a contract for the construction of 9157 - Fire Station No. 8 Relocation Project to the lowest responsive, responsible bidder D.L. Falk Construction, Inc., for the base bid in the amount of $10,526,000 and approve a 10% contingency in the amount of $1,052,600.

(c) Adopt the following 2023-2024 Appropriation Ordinance amendments in the Public Safety and Infrastructure Bond Fund (498): 

 (1) Increase the Measure T - Fire Station 8 Relocation appropriation in the amount of $1,687,000; and

 (2) Decrease the Measure T - Program Reserve (Public Safety) appropriation by $1,687,000.

(d) In accordance with City Council-approved Budget Principle #8, certify that funding the annual operations and maintenance costs for Fire Station 8, which is estimated to exceed $100,000 annually in the General Fund once the project is complete, will not require a decrease in existing basic neighborhood services.

CEQA: Fire Station No. 8 Relocation Project Initial Study/Mitigated Negative Declaration, File No. ER22-063. Council District 3. (Public Works/City Manager)