...Title
Report on Bids and Award of Contract for the 10087 - Center for the Performing Arts Chiller, Cooling Tower, and Boiler Replacement Project.
...Recommendations
(a) Report on bids and award of a contract for the construction of 10087 - Center for the Performing Arts Chiller, Cooling Tower, and Boiler Replacement Project to the lowest responsive, responsible bidder, Mesa Energy Systems Inc., for the base bid and Bid Alternate No. 1 in the amount of $5,940,284; and
(b) Approve a 15% contingency in the amount of $891,043.
CEQA: Categorically Exempt, File No. ER25-085, CEQA Guidelines Section 15302 – Replacement and Construction. Council District 3. (Public Works)