...Title
Construction Contract Contingency Increase for the 10106 - South Bay Water Recycling Pump Station 5 Bypass Project Rebid.
...Recommendations
Approve a $24,200 increase to the construction contingency amount of $18,000 for a revised total contingency amount of $42,200 for the 10106 - South Bay Water Recycling Pump Station 5 Bypass Project Rebid.