...Title
Actions Related to the 10180 - SJC New Taxiway Victor Phase 3A.
...Recommendations
Adopt a resolution authorizing the Director of Public Works, or his designee to:
(a) Award and execute a construction contract for 10180 - SJC New Taxiway Victor Phase 3A to the lowest responsive, responsible bidder, in an amount not to exceed $15,215,000;
(b) Decide any timely bid protest(s) and make the City’s final determination as to the lowest responsive bidder that is responsible as needed to award the contract; and
(c) Approve a contingency of up to 10% of the amount of the contract for the construction of the project.
CEQA: Determination of Consistency with the San José Mineta International Airport Master Plan Amendment Environmental Impact Report, File No. ER22-021 (Resolution No. 79497). (Public Works/Airport)