Actions Related to the 9405-Norman Y. Mineta San José International Airport Perimeter Protection Project Re-Bid II Project.
...Recommendations
(a) Report on bids and award of contract for the 9405 - Norman Y. Mineta San José International Airport Perimeter Protection Project Re-Bid II Project to the lowest responsive bidder, Rosendin Electric, Inc., for the base bid and Bid Alternate No. 1 in an amount of $2,999,385.75.
(b) Approve a 10 percent contingency in the amount of $299,939.
(c) Adopt the following 2022-2023 Appropriation Ordinance amendments in the Airport Revenue Fund:
(1) Decrease the Airline Agreement Reserve by $1,282,000; and
(2) Increase the Transfer to the Airport Surplus Revenue Fund by $1,282,000.
(d) Adopt the following 2022-2023 Appropriation Ordinance and Funding Sources Resolution amendments in the Airport Surplus Revenue Fund:
(1) Increase the estimate for Transfers and Reimbursements by $1,282,000; and
(2) Increase the Transfer to the Airport Renewal and Replacement Fund by $1,282,000.
(e) Adopt the following 2022-2023 Appropriation Ordinance and Funding Sources Resolution amendments in the Airport Renewal and Replacement Fund:
(1) Increase the estimate for Transfers and Reimbursements by $1,282,000; and
(2) Increase the Perimeter Security Projects appropriation in the amount of $1,282,000.
CEQA: File No. PP18-103, Environmental Impact Report for the Amendment to the Norman Y. Mineta San Joseì International Airport Master Plan (Resolution No. 79497). (Airport/Public Works/City Manager)