Actions Related to the 9375 - Market Street Garage Improvements Project.
...Recommendations
(a) Approve an increase to the construction contingency for 9375 - Market Street Garage Improvements Project from 15% to 34%, in the amount of $1,156,215, from $912,801 to $2,069,016.
(b) Adopt the following Fiscal Year 2026-2027 Appropriation Ordinance amendments in the General-Purpose Parking Capital Fund:
(1) Increase the Garage Façade Improvements appropriation to the Transportation Department by $1,831,000; and
(2) Decrease the Unrestricted Ending Fund Balance by $1,831,000.
CEQA: Categorically Exempt, File No. ER20-225, CEQA Guidelines Section 15301, Existing Facilities. Council District 3. (Public Works/Transportation/City Manager)
[Deferred from 6/9/2026 - Item 2.10 (26-680)]