...Title
Report on Bids and Award of Contract for the 10085 - Sanitary Sewer Repairs Fiscal Year 2022-2023 Package III Project.
...Recommendations
(a) Report on bids and award of contract for the construction of 10085 - Sanitary Sewer Repairs Fiscal Year 2022-2023 Package III Project to the lowest responsive, responsible bidder, SubTerra Construction, Inc., in the amount of $2,775,574; and
(b) Approve a 10% contingency in the amount of $277,557.
CEQA: Exempt, File No. ER23-189, CEQA Guidelines Sections 15301(b) Existing Facilities, and 15302(c)Replacement or Reconstruction. Council Districts 3, 6, and 7. (Public Works)