Report on Bids and Award of Contract for the 10288-Sanitary Sewer Repairs Fiscal Year 2023 2024 Package I Project.
...Recommendations
(a) Report on bids and award of contract for the construction of 10288-Sanitary Sewer Repairs Fiscal Year 2023-2024 Package I Project, to the lowest responsive, responsible bidder, Sancon Technologies, Inc., in the amount of $1,647,514; and
(b) Approve a 10% contingency in the amount of $164,751.
CEQA: Exempt, File No. ER23-189, CEQA Guidelines Sections 15301(b) Existing Facilities, and 15302(c) Replacement or Reconstruction. Council District 9. (Public Works)