...Title
Award of Dewatered Biosolids Transportation and Beneficial Use Service Agreements for the San José-Santa Clara Regional Wastewater Facility.
...Recommendations
(a) Adopt a resolution adopting the Addendum to the Environmental Impact Report for the San José-Santa Clara Water Pollution Control Plant Master Plan (SCH #2011052074), Biosolids Disposition Project, File No. ER20-129, in accordance with the California Environmental Quality Act (CEQA), as amended.
(b) Approve and execute the following dewatered biosolids transportation and beneficial use service agreements to manage the dewatered biosolids produced annually by the San José-Santa Clara Regional Wastewater Facility:
(1) Denali Water Solutions, LLC to manage approximately 35% of the dewatered biosolids produced annually by the San José-Santa Clara Regional Wastewater Facility through June 30, 2029, with options to extend through June 30, 2033, and a maximum compensation of $18,400,000, subject to the appropriation of funds.
(2) Synagro West, LLC to manage approximately 57% of the dewatered biosolids produced annually by the San José-Santa Clara Regional Wastewater Facility through June 30, 2029, with options to extend through June 30, 2033, and a maximum compensation of $29,600,000, subject to the appropriation of funds.
(3) Lystek International Limited to manage approximately 8% of the dewatered biosolids produced annually by the San José-Santa Clara Regional Wastewater Facility through June 30, 2029, with options to extend through June 30, 2033, and a maximum compensation of $7,300,000, subject to the appropriation of funds.
(c) Adopt a resolution delegating authority to the City Manager or their designee to negotiate and execute amendments to the biosolid transportation and beneficial use service agreements with Denali Water Solutions, LLC, Synagro West, LLC, and Lystek International Limited to account for necessary changes to the percentage of the dewatered biosolids managed under each agreement and the corresponding compensation and/or execute extensions to the initial term of the agreement so long as such amendments do not exceed the combined total of $55,300,000.
CEQA: Addendum to the Environmental Impact Report for the San José - Santa Clara Water Pollution Control Plant Master Plan (SCH #2011052074), Biosolids Disposition Project, File No. ER20-129. (Environmental Services)