Title: Construction Contingency Increase for the 7418 - Cogeneration Facility Project at the San José - Santa Clara Regional Wastewater Facility and Appropriation Amendments.
Attachments: 1. Memorandum, 2. Supplemental Memorandum, 1/15/2021

...Title

Construction Contingency Increase for the 7418 - Cogeneration Facility Project at the San José - Santa Clara Regional Wastewater Facility and Appropriation Amendments.

...Recommendations

(a)                     Approve a $1,900,000 increase to the owner-controlled construction contingency for the 7418 - Cogeneration Facility Project (“Project”) for a revised contingency in an amount not to exceed $10,188,000.

(b)                     Adopt a resolution authorizing the City Manager to negotiate and execute amendments to the Design-Build Contract to include additional work and services required to complete the Project or requested by the City, pay for costs resulting from the COVID-19 pandemic and increase the Guaranteed Maximum Price from $91,172,000 to $93,072,000.

(c)                     Adopt the following 2020-2021 Appropriation Ordinance Amendments in the San José-Santa Clara Treatment Plant Capital Fund:

 (1)                     Decrease the Nitrification Clarifier Rehabilitation appropriation to the Environmental Services Department by $1,900,000; and

 (2)                     Increase the Energy Generation Improvements appropriation to the Environmental Services Department by $1,900,000.

CEQA: San José/Santa Clara Regional Wastewater Facility Cogenerator Project Mitigated Negative Declaration, File No. PP14-005 and Addendum Mitigated Negative Declaration, File No. PP16-009. (Environmental Services/Public Works/City Manager)