...Title
Report on Bids and Award of Contract for 8927 - Fowler Pump Station Replacement Project.
...Recommendations
(a) Report on bids and award of contract for 8927 - Fowler Pump Station Replacement project to the low bidder, JMB Construction, Inc., in an amount not to exceed $2,759,500 and approval of a project contingency in the amount of $551,900.
(b) Adopt the following 2019-2020 Appropriation Ordinance amendments in the Water Utility Capital Fund:
(1) Increase the Fowler Pump Station Replacement appropriation to the Environmental Services Department in the amount of $1,190,000; and
(2) Decrease the Unrestricted Ending Fund Balance by $1,190,000.
CEQA: Categorically Exempt, File No. PP19-034, CEQA Guidelines Section 15301(b), Existing Facilities. Council District 8. (Environmental Services/City Manager)