Title: Actions Related to the 7382-Digester and Thickener Facilities Upgrade Project at the San Jose-Santa Clara Regional Wastewater Facility.
Attachments: 1. Memorandum, 2. TPAC Supplemental Memorandum, 3. Resolution 77758, 4. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

...Title

Actions Related to the 7382-Digester and Thickener Facilities Upgrade Project at the San Jose-Santa Clara Regional Wastewater Facility.

...Recommendations

a. Approve a $25,000,000 increase to the construction contingency amount of $28,490,625 for a revised total contingency amount of $53,490,625 and increasing the contract not-to-exceed amount from $136,415,625 to a total revised contract amount not-to-exceed $161,415,625 for the 7382 - Digester and Thickener Facilities Upgrade Project.

b. Adopt the following 2017-2018 Appropriation Ordinance Amendments in the San José- Santa Clara Treatment Plant Capital Fund:

1. Decrease the Aeration Tanks and Blower Rehabilitation Appropriation by $18,000,000;

2. Decrease the Urgent and Unscheduled Treatment Plant Rehabilitation Appropriation by $4,500,000;

3. Decrease the Advance Facility Control and Meter Replacement Appropriation by $4,000,000; and

4. Increase the Digester and Thickener Facilities Upgrade Appropriation Environmental Services Department by $26,500,000.

CEQA: Mitigated Negative Declaration for the San José-Santa Clara Regional Wastewater Facility Digester and Thickener Facilities Upgrade Project (Resolution No. 77758), File No. PP15-055. (Public Works/City Manager)