Actions Related to the 7382-Digester and Thickener Facilities Upgrade Project at the San Jose-Santa Clara Regional Wastewater Facility.
...Recommendations
a. Approve a $25,000,000 increase to the construction contingency amount of $28,490,625 for a revised total contingency amount of $53,490,625 and increasing the contract not-to-exceed amount from $136,415,625 to a total revised contract amount not-to-exceed $161,415,625 for the 7382 - Digester and Thickener Facilities Upgrade Project.
b. Adopt the following 2017-2018 Appropriation Ordinance Amendments in the San José- Santa Clara Treatment Plant Capital Fund:
1. Decrease the Aeration Tanks and Blower Rehabilitation Appropriation by $18,000,000;
2. Decrease the Urgent and Unscheduled Treatment Plant Rehabilitation Appropriation by $4,500,000;
3. Decrease the Advance Facility Control and Meter Replacement Appropriation by $4,000,000; and
4. Increase the Digester and Thickener Facilities Upgrade Appropriation Environmental Services Department by $26,500,000.